Eskom in hot water after multiple warnings about nuclear compliance problems at Koeberg
- Eskom was required to install hardened water connection points by 31 October 2025, which it failed to achieve, resulting in non-compliance with certain conditions of its licence.
- The regulator issued Eskom with a directive under the National Nuclear Regulator Act for non-compliance with its licence conditions, citing inadequate quality control of end-of-manufacturing records prior to implementation of the modification of the plant.
- The National Nuclear Regulator (NNR) issued four enforcement actions against Eskom for non-compliance at the Koeberg Nuclear Power Station in the NNR’s 2025/26 financial year.