R164 million spent to construct a new Magistrate’s Court building which remains incomplete 12 years later
- The Department of Public Works has appointed a new contractor under a R241.26 million contract to complete the Mamelodi Magistrate’s Court, with the project now expected to be completed within 24 months, by October 2028.
- The original completion date was May 2015, but the project made little progress and was eventually abandoned after the original contractor, Fikile Construction, was terminated in October 2023.
- The cost of the unfinished project had also increased substantially, with R163.94 million spent on the project by October 2025, and the department intends to take legal action against Fikile Construction to recover damages caused by the incomplete work.
Stay informed. More top South African stories on The Feed SA · Follow on Facebook